Situation

  • The Queen Alexander Bridge – the existing power supply route - was due to be decommissioned due to age and phasing out oil-filled cables in favour of the New Wear Bridge.

  • Northern Power Grid required a unique installation involving power cables being suspended under the bridge and above the water in Emtelle ducts.

  • Balfour Beatty contracted to install cables and sought Ellis for duct support solution.

Solution

  • Ellis collaborated with Balfour Beatty:

  • Developed a product to suspend ducts beneath the bridge.

  • Created an installation methodology.

  • Solution involved 12 standard 2F+ clamps with a customised bespoke stainless-steel structure.

  • Supplied a total of 240 assemblies.

  • Frames hang below the bridge, supporting Emtelle ducts, with power cables installed within these ducts.