Severn Tunnel Electrification, Network Rail
Date Oct 2016
Project Name Severn Tunnel Electrification Upgrade
Distributor ETS
Project Location Rogiet, Monmouthshire, Wales
Scope of supply Standard 2F+ clamps complete with stainless steel support framework
Situation
• Network rail required a solution to carry the insulated ATF Cable required in the electrification of the Severn Tunnel project.
• The solution had to withstand the aggressive conditions as well as ensure a 40-year product design life.
Solution
• Ellis worked closely with Network Rail to adapt the proven 2F cable guide clamp by creating a bespoke fixing bracket that was manufactured in-house from Super Duplex Stainless Steel.